M10-03 Knowledge Transfer Sessions¶
Milestone: M10 — Deployment / Go-Live and Handover SOW Reference: Deliverable D7 Requirement Clarity: ✅ Clear Dev Status: ❌ Not started
Overview¶
Deliver recorded knowledge-transfer sessions to the JVP before acceptance, covering operation, support and maintenance of the platform.
Tasks¶
- Administrator training session
- Support team handover session
- Technical architecture walkthrough
- Deployment walkthrough
- Integration walkthrough
- Operational support walkthrough
- Record all sessions and supply to the JVP
Dependencies¶
- M10-02 documentation pack — sessions should walk through this material.
Acceptance Criteria¶
- Knowledge transfer sessions completed
- All sessions recorded and supplied to the JVP (per SOW Appendix 6, "Knowledge Transfer")
Existing Reference Material¶
- SOW Appendix 6, "Knowledge Transfer" section
Blockers & Risks¶
None identified — mostly a scheduling/logistics task once the platform is stable.