M10 — Deployment / Go-Live for Release v1.0 General Use; Handover / Project Closure¶
SOW Deliverable(s): D6 (Documentation Pack), D7 (Handover Materials) Requirement source: SOW §8, Appendix 6 (Deliverables for Handover), "End User Beta Programme and Final Acceptance" section
Tasks¶
| ID | Task | SOW Ref | Requirement Clarity | Dev Status | Task File |
|---|---|---|---|---|---|
| M10-01 | Production deployment / go-live readiness | D5/D6 | ⚠️ Blocking — sequencing ambiguity, see task file | ❌ Not started | M10-01-production-deployment-go-live-readiness.md |
| M10-02 | Technical documentation pack — architecture, API, deployment, data model, security docs | D6 | ✅ | 🟡 | M10-02-technical-documentation-pack.md |
| M10-03 | Knowledge transfer sessions — admin training, support handover, technical/deployment/integration/ops walkthroughs (recorded, supplied to JVP) | D7 | ✅ | ❌ Not started | M10-03-knowledge-transfer-sessions.md |
| M10-04 | Source code & repository handover, incl. Infrastructure-as-Code | D7, NFR6 | ✅ | ❌ Not started | M10-04-source-code-repository-handover.md |
| M10-05 | End User Beta Programme execution & Final Acceptance | SOW §Beta Programme | ✅ | ⚪ Not started | M10-05-end-user-beta-programme-final-acceptance.md |
| M10-06 | Regression testing & Critical/High defect remediation post-beta | SOW §Beta Programme | ✅ | ⚪ Not started | M10-06-regression-testing-defect-remediation.md |
Notes¶
M10-01's sequencing ambiguity is the single most important requirement question to resolve for this milestone: does "go-live" at M10 mean the same thing as "Final Acceptance," given Final Acceptance is separately defined to only occur after the Beta Programme completes. Recommend getting written agreement from Curo on which definition governs.