M10 — Deployment / Go-Live for Release v1.0 General Use; Handover / Project Closure

SOW Deliverable(s): D6 (Documentation Pack), D7 (Handover Materials) Requirement source: SOW §8, Appendix 6 (Deliverables for Handover), "End User Beta Programme and Final Acceptance" section

Tasks

ID Task SOW Ref Requirement Clarity Dev Status Task File
M10-01 Production deployment / go-live readiness D5/D6 ⚠️ Blocking — sequencing ambiguity, see task file ❌ Not started M10-01-production-deployment-go-live-readiness.md
M10-02 Technical documentation pack — architecture, API, deployment, data model, security docs D6 🟡 M10-02-technical-documentation-pack.md
M10-03 Knowledge transfer sessions — admin training, support handover, technical/deployment/integration/ops walkthroughs (recorded, supplied to JVP) D7 ❌ Not started M10-03-knowledge-transfer-sessions.md
M10-04 Source code & repository handover, incl. Infrastructure-as-Code D7, NFR6 ❌ Not started M10-04-source-code-repository-handover.md
M10-05 End User Beta Programme execution & Final Acceptance SOW §Beta Programme ⚪ Not started M10-05-end-user-beta-programme-final-acceptance.md
M10-06 Regression testing & Critical/High defect remediation post-beta SOW §Beta Programme ⚪ Not started M10-06-regression-testing-defect-remediation.md

Notes

M10-01's sequencing ambiguity is the single most important requirement question to resolve for this milestone: does "go-live" at M10 mean the same thing as "Final Acceptance," given Final Acceptance is separately defined to only occur after the Beta Programme completes. Recommend getting written agreement from Curo on which definition governs.