M10-05 End User Beta Programme Execution & Final Acceptance

Milestone: M10 — Deployment / Go-Live and Handover SOW Reference: SOW "End User Beta Programme and Final Acceptance" section Requirement Clarity: ✅ Clear Dev Status: ⚪ Not started — depends on the Feature Complete Release existing first

Overview

Following delivery of a Feature Complete Release, Curo has a preparation period to complete deployment, beta-user onboarding, and supporting documentation. After that, the End User Beta Programme runs with a limited group of nominated REC member Staffing Companies validating the solution under real conditions.

Tasks

  • Confirm the Feature Complete Release definition and date with Curo
  • Support the preparation period per SOW terms
  • Provide reasonable support throughout the Beta Programme
  • Investigate and rectify any Critical or High-Priority Defects found during Beta

Dependencies

  • Every feature milestone (M2-M9) needs to be substantially complete before the Feature Complete Release can happen.
  • M10-01 go-live readiness — Final Acceptance timing is directly tied to this.
  • M10-06 regression testing — runs after each remedial release during Beta.

Acceptance Criteria

  • Successful completion of the preparation period and Beta Programme
  • Remediation of all agreed Critical and High-Priority Defects (per SOW, "End User Beta Programme and Final Acceptance")

Existing Reference Material

  • SOW, "End User Beta Programme and Final Acceptance" section

Blockers & Risks

None beyond the general dependency on prior milestones being complete.